(+91) 97260 97222

We are open 9 AM - 6 PM

shreeyaent2000@gmail.com

You can mail us
ONGC PETRO ADDITION LTD. - 2016-2017
Locaion : (Dahej Gujarat) Industry : ONGC PETRO ADDITION LTD. Owner : ONGC PETRO ADDITION LTD. Status : Completed Date : 14th July, 2025

ONGC PETRO ADDITION LTD. - 2016-2017

  • Fabrication  &
    Erection of AG unit
    Piping Work.
  • Fabrication & Erection of AG (Above Ground) Unit Piping Work

  • Fabrication refers to the cutting, shaping, and assembling of pipes in a controlled environment, usually a workshop.

  • Erection involves the installation and alignment of prefabricated pipe sections at the actual site location.

  • AG Unit Piping stands for Above Ground piping systems used to carry liquids or gases across industrial units without underground laying.

  • All work is done according to P&ID (Piping and Instrumentation Diagrams) and isometric drawings approved by the engineering team.

  • Materials typically include Carbon Steel (CS), Stainless Steel (SS), and Alloy Steel depending on the fluid type and temperature.

  • Pipe spools are fabricated by cutting, beveling, and welding of elbows, tees, reducers, and flanges to the required specification.

  • A fit-up inspection is conducted before welding to ensure correct alignment and gap tolerance.

  • Welds are done as per Welding Procedure Specification (WPS) using qualified welders under strict supervision.

  • NDT (Non-Destructive Testing) such as radiography or dye penetrant tests is done to ensure weld quality.

  • After fabrication, spools are hydrotested (or pneumatically tested) to verify pressure integrity.

  • Fabricated spools are transported to the site with care using rigging tools and lifting equipment.

  • Site erection includes lifting, placing, and aligning the spools using cranes, chain pulleys, and jacks.

  • Pipe supports, hangers, and guides are installed to accommodate thermal expansion and load-bearing.

  • Final welds and connections are made on-site with high precision and safety compliance.

  • The pipeline is then flushed and cleaned using air, water, or chemical flushing as per the service type.

  • After installation, another hydrotest is performed to ensure there are no leaks under pressure.

  • All erection and welding activities are logged in inspection reports, test certificates, and handover documents.

  • Throughout the process, safety protocols like PPE, scaffolding, and permits are strictly enforced.

  • Coordination with civil, electrical, and instrumentation teams is crucial to avoid clashes.

  • The final system is commissioned, ensuring it is ready for operational use with proper documentation and client approval.